Kemble Drainage Improvement Project

Share Kemble Drainage Improvement Project on Facebook Share Kemble Drainage Improvement Project on Twitter Share Kemble Drainage Improvement Project on Linkedin Email Kemble Drainage Improvement Project link

Drainage upgrades are coming to the Village of Kemble. The Township of Georgian Bluffs is planning infrastructure improvements at the intersection of Kemble Rock Road and Concession 20.

This work is tentatively scheduled to start spring 2026 and be completed by fall of 2026, pending budget and Council approval. It includes new culverts, ditches, and stormwater systems. The Township is asking for your feedback to help guide the design and address long-standing drainage concerns in Kemble.

Public Information Centre (PIC):
πŸ“… November 25, 2025 | πŸ•” 5:00–7:00 p.m.
πŸ“ Kemble Arena – 319897 Kemble Rock Rd, Kemble, ON

Comment period open until: πŸ—“οΈ December 23, 2025


We value your input! You can:

  • Attend the Public Information Centre

  • Submit comments using the online form or hardcopy comment sheet available at the above PIC

  • Contact project representatives directly

Drainage upgrades are coming to the Village of Kemble. The Township of Georgian Bluffs is planning infrastructure improvements at the intersection of Kemble Rock Road and Concession 20.

This work is tentatively scheduled to start spring 2026 and be completed by fall of 2026, pending budget and Council approval. It includes new culverts, ditches, and stormwater systems. The Township is asking for your feedback to help guide the design and address long-standing drainage concerns in Kemble.

Public Information Centre (PIC):
πŸ“… November 25, 2025 | πŸ•” 5:00–7:00 p.m.
πŸ“ Kemble Arena – 319897 Kemble Rock Rd, Kemble, ON

Comment period open until: πŸ—“οΈ December 23, 2025


We value your input! You can:

  • Attend the Public Information Centre

  • Submit comments using the online form or hardcopy comment sheet available at the above PIC

  • Contact project representatives directly

  • Project Overview

    Share Project Overview on Facebook Share Project Overview on Twitter Share Project Overview on Linkedin Email Project Overview link
    supporting image

    The Township has retained Pearson Engineering Ltd. to complete the detailed design for this infrastructure upgrade.

    Goals of the Project:

    • Improve stormwater drainage

    • Replace aging infrastructure

    • Reduce erosion and flooding issues

    What’s Being Done

    Based on engineering studies and field assessments, the following work is proposed:

    βœ… Replace roadway and driveway culverts
    βœ… Install new stormwater catch basins and underground pipes
    βœ… Remove heavy vegetation from ditches
    βœ… Re-grade and re-shape ditches with rock protection
    βœ… Replace curbs, gutters, and asphalt shoulders
    βœ… Repave the asphalt road surface

    Budget:

    The Townhsip has budgeted $950,000 for this project.

    Project Timeline

    • Public Information Centre (PIC):
      πŸ“… November 25, 2025
      πŸ•” 5:00 p.m. to 7:00 p.m.
      πŸ“ Kemble Arena – 319897 Kemble Rock Rd, Kemble, ON

    • Public Comment Period:
      πŸ—“οΈ November 25 to December 23, 2025

    • Construction Timeline:
      πŸ—οΈ Begin: Spring of 2026
      End: Fall of 2026


  • What to Expect During Construction

    Share What to Expect During Construction on Facebook Share What to Expect During Construction on Twitter Share What to Expect During Construction on Linkedin Email What to Expect During Construction link

    πŸ—‘οΈ Garbage and Recycling Collection:

    The Contractor will be responsible throughout construction to collect garbage from residents within limits of construction.

    πŸ…ΏοΈ Driveway Access:

    Restrictions to driveway access will be limited as much as possible. Where unavoidable, the Contractor will be required to provide and maintain temporary parking.

    🚧 Traffic Interruptions:
    Temporary road closures will take place during phased construction. Detours will be in place, and local access will be maintained.

    πŸ”‡ Construction Hours:

    To mitigate impacts to local residents, construction will be limited to 7am to 7pm each day. No weekend or stat holiday work permitted. The Contractor will control dust on site and will ensure the construction site remains clean as much as possible.

    πŸ’‘ Utilities:

    Minor impacts to utilities services are anticipated throughout construction. Where service disruptions are anticipated, notices will be issued to residents.

    🌳 Tree Removals:

    Tree removals on site will be limited as much as possible. No tree removals will be completed on private property. It is the goal of the Township to maintain trees on-site.

Page published: 07 Nov 2025, 11:41 AM